DETAILED FEASIBILITY STUDY

   Oct. '14 to May. '15

960 MW JANGI THOPAN POWARI  PROJECT, HP

SCOPE OF WORKS

    • Bid Parameter Advice – Viability and Market (Competitor & Tariff) Analysis [Including tariff projection and financial modelling]
    • Hydrology & Power Potential Study
    • Designs and BoQ for Main Civil Works, Transmission Line Works
    • Review and Updation of BoQ for Hydro Mechanical & Electro-Mechanical (E-M) Works
    • Hard Cost Estimation for Civil, Hydro-Mechanical and E-M Works
    • Development Cost Estimation
    • Construction Methodology, Equipment Selection, Construction Schedule & Cost Estimation